PROJECTS BY OWNER

Projects by type

State University of NY Construction Fund

  • State University of NY Construction Fund
    Delivered: PFS processes for site improvement/new construction
    for college campuses in Farmingdale, Stony Brook, Long Island; Purchase and New Paltz, NY.

CT Department of Transportation

  • Delivered: PFS/PLA processes for highway/bridge improvement projects in New London (3), Hartford, Meriden-Middletown, (3), Norwalk, East Lyme, West Hartford. Railroad station rehab projects in Windsor Lock, Naugatuck and Hartford.

NYS Office of General Services

  • Delivered:PFS/PLA processes for rehab new construction for Creedmoor, Kirby and Manhattan Psychiatric mental health facilities (5); Jamaica and Lexington Avenue armories (3), Hunter and Baruch colleges (5).

Ulster County NY

  • Delivered: Delivered: PFS/PLA processes for new County Government Center, Family Court, Cooper Dam, Dietz Stadium.

U.S. Department of Veterans Services

  • Delivered: Delivered: PFS process for site improvements/new construction at Fort Snelling Federal Cemetery, Minneapolis, MN.

Dutchess County, NY

  • Delivered: PFS/PLA processes for rehab/new construction at a downtown Municipal Building, Youth Center, Justice Transition Center, Poughkeepsie School District; Dutchess County Baseball Stadium, Mid-Hudson Bridge Decking Replacement.

Rockland County, NY

  • Delivered: PFS processes for upgrades and new construction in the sewer district: Main Pump and Sludge Dewatering System; construction of a new Materials Recycling Facility, Utility Building E and Animal shelter.

RECENT PROJECTS

Creedmoor Psychiatric Center

  • Project owner: NYS Department of Mental Health
  • Delivered: PFS/PLA for rehab Building 40
  • Date: Phase 1: September 2019-March 2020
  • Date: Phase 2: February 2023-June 2024

Creedmoor Psychiatric Center

  • Project owner: OGS
  • Delivered: Addendum to prior PFS/PLA
  • Date: Phase 1: January 2021-August 2021
  • Date: Phase 2: May-December 2024

Improvements I-91/691, Meriden

  • Project owner: CTDOT
  • Delivered: PFS for new construction and rehab
  • Date: Phase 1: June 2021-April 2022
  • Date: Phase 2- September 2023-December 2024

Gold Star Bridge

  • Project owner: CTDOT
  • Delivered: PFS/PLA for bridge rehab
  • Date: Phase 1: January 2021-January 2022
  • Date: Phase 2: August 2023-December 2024

Manhattan Psychiatric Extension

  • Project owner: NYS Office of Mental Health
  • Delivered: PFS for new construction and rehab
  • Date: Phase 1: March-May 2022
  • Date: Phase 2: March-August 2023

Lexington Avenue Armory

  • Project owner: NYS Department of Military Affairs
  • Delivered: PFS new construction/rehab
  • Date: October 2021-June 2022

I-95 Improvements Exchange 74, East Lyme

  • Project owner: CTDOT
  • Delivered: PFS/PLA for new construction and rehab
  • Date: October 2021-June 2022

Poughkeepsie School District

  • Project owner: Dutchess County
  • Delivered: PFS/PLA for rehab/new construction
  • Date: October 2021-January 2022

Jamaica Armory

  • Project owner: NYS Office of General Services
  • Delivered: PFS/PLA for rehab and new construction
  • Date: September 2019-July 2020

Newburgh Expanded City School District

  • Project owner: Newburgh Board of Education
  • Delivered: PFS new construction and rehab; PLA
  • Date: May 2020 – July 2020

Bedford Community House

  • Project owner: Town of Bedford Hills
  • Delivered: PFS interior development and rehab
  • Date: February-March 2020

Jamaica Armory

  • Project owner: NYS Office of General Services
  • Delivered: PFS rehab and new construction; PLA
  • Date: September 2019 – July 2020

Creedmoor Psychiatric Center

  • Project owner: NYS Office of General Services
  • Delivered: PFS rehab Building 40; PLA
  • Date: September 2019 – March 2020

Justice and Transition Center

  • Project owner: Dutchess County
  • Delivered: PFS new jail; PLA
  • Date: March - July 2019

Hutchinson Elementary School

  • Project owner: Pelham Central School District
  • Delivered: PFS new school; PLA
  • Date: January - September 2019

Safety and Operational Improvements I-84

  • Project owner: CT Department of Transportation
  • Delivered: PFS highway project; PLA
  • Date: January-September 2019

Transfer Station

  • Project owner: Orange County
  • Delivered: PFS new facility; PLA
  • Date: March - September 2019

Deck Replacement Mid-Hudson Bridge

  • Project owner: NYS Bridge Authority
  • Delivered: PFS rehab north span; PLA
  • Date: October - September 2019

Maybrook Bikeway Path II

  • Project owner: Putnam County
  • Delivered: PFS construction of bike trail
  • Date: December 2018

Maplethorpe Pedestrian Bridge

  • Project owner: Putnam County
  • Delivered: Qualifying Assessment
  • Date: September - December 2018

Alternations to Fire Stations

  • Project owner: Village of Mt. Kisco, NY
  • Delivered: PFS upgrading fire services; PLA
  • Date: September 2018

Water Main Replacement

  • Project owner: Village of Mt. Kisco, NY
  • Delivered: PFS upgrading infrastructure; PLA
  • Date: June 2018

Renovation Police HQ

  • Project owner: Village of Mt. Kisco, NY
  • Delivered: PFS renovation existing building; PLA
  • Date: January 2018

Shirley Chisholm Office Building

  • Project owner: NYS Office of General Services
  • Delivered: PFS repair existing façade; PLA
  • Date: January-June 2018
Projects by type